UIG FERRY TERMINAL

Location
Isle of Skye

Customer
Concrete Repairs Limited

Type
Infrastructure

Access Solutions Scaffolding - Delivering Innovative Solutions for the Uig Ferry Terminal Upgrade

We are delighted to share our experience working on the Phase One upgrade and redevelopment of the Uig Ferry Terminal, a project initiated by The Highland Council to accommodate the growing demand in Scottish tourism. Our team at played a pivotal role in transforming the Approach Way, setting the stage for further enhancements at the terminal.

The complexity of this project required out-of-the-box thinking, leading us to deploy a 125m long hanging scaffold suspended from the road side, over the edge, and back underneath at varying heights of 6m and 12m. This innovative solution, supported by Apollo bolts fixed to the wall face, formed the backbone for a bridged structure comprising tube and fitting, aluminium beams, and Layher Decks.

One notable aspect of our approach was the utilisation of three different scaffold systems in a single structure—a departure from industry norms necessitated by the full submergence of the scaffold during high tide. By integrating Layher Decks that could accommodate rising and falling water levels without compromising structural integrity, we minimised the need for extensive remedial work, ensuring efficient progress and timely delivery for our client.

Adhering to a stringent schedule dictated by tides, our dedicated operatives worked tirelessly around the clock to meet project milestones and overcome logistical challenges. As Phase One neared completion, our focus shifted to Phase Two, which commenced at the Pier Head in spring 2023.

At Access Solutions Scaffolding, we pride ourselves on our ability to adapt, innovate, and deliver exceptional results even in the most demanding environments. Stay tuned as we continue to play a key role in the transformation of the Uig Ferry Terminal, shaping a brighter future for Scottish tourism.

Concrete Repairs Limited
Gary Dunlop, Contracts Manager

CRL engaged with A/S/S for this project at very short notice and tasked them with providing a complex working platform to fit our requirements for carrying out over 50m3 of soffit and beam concrete repairs over the full length of the pier approach way. The guys at A/S/S pulled out all the stops to have men and materials on site as soon as possible and have design drawings combined with CAT 3 checks completed to allow us to maintain our programme and give us continuity of work for the full duration of phase 1.

Very well done to all at A/S/S involved in phase 1 of this very challenging project.

Next
Next

The Glenturret Distillery, Creiff